Accession Number:

ADA626566

Title:

AGOR 28: SIO Shipyard Representative Bi-Weekly Progress Report

Descriptive Note:

Progress rept.

Corporate Author:

SCRIPPS INST OF OCEANOGRAPHY SAN DIEGO NIMITZ MARINE FACILITY

Personal Author(s):

Report Date:

2015-07-02

Pagination or Media Count:

6.0

Abstract:

Progress on the building of AGOR 28, oceanographic research vessel Sally Ride. Work continues on initial outfitting lists for Sally Ride and NS5 Hierarchy. No additional acoustic tiles have been removed this reporting period. The yard has covered the tiles in the HVAC and MSD spaces with insulation and Quadzero. The yard has covered the tiles on the upper level of the Main Machinery Space on the port side with insulation and Quad-zero. The port and starboard sides of the lower level of the Main Machinery space are the on only areas to have exposed tile that is to be covered by insulation and Quad-zero. During load bank testing of the Generator Sets, the noise profile on Ride s back deck was very similar to that found on Armstrong. Baffles had minimal affect in reduce the noise on Armstrong. No indication as of yet what is being done to correct this issue. Hydraulic System flushing and pressure testing is ongoing

Subject Categories:

  • Marine Engineering

Distribution Statement:

APPROVED FOR PUBLIC RELEASE