AGOR 28, SIO Shipyard Representative Bi-Weekly Progress Report

Descriptive Note:

Progress rept.

Corporate Author:

SCRIPPS INST OF OCEANOGRAPHY SAN DIEGO NIMITZ MARINE FACILITY

Personal Author(s):

Report Date:

2014-12-04

Pagination or Media Count:

12.0

Abstract:

Progress on the building of AGOR 28, oceanographic research vessel Sally Ride. Work continues 1 reviewing Vendor Recommended Spares VRS 2 reviewing Technical Manuals and Supplemental Information 3 work on initial outfitting lists for Sally Ride and working on NS5 Hierarchy. Intermediate Shaft Bearings have been installed on Ride s modified foundations. Alignment in progress on both vessels. Unresolved issues with fairlead interferences from TK70-70 main crane remain. DCI is using Sally Rides aft fairlead foundation to test various new locations on Armstrong.