The Department of the Navy Spent Recovery Act Funds on Photovoltaic Projects That Were Not Cost-Effective
Descriptive Note:
Congressional rept.
Corporate Author:
INSPECTOR GENERAL DEPT OF DEFENSE ARLINGTON VA
Personal Author(s):
Report Date:
2011-09-22
Pagination or Media Count:
91.0
Abstract:
Our overall objective was to evaluate DoD s implementation of Public Law 111-5, American Recovery and Reinvestment Act of 2009 Recovery Act, February 17, 2009. Specifically, we determined whether the Department of the Navy planned and selected 3 photovoltaic PV projects at 12 Navy and Marine Corps sites in accordance with the Recovery Act and applicable legislation and policies. We reviewed Project P856-M at Marine Corps Base Camp Pendleton Camp Pendleton, Project RM09-1363 at Navy installations in Hawaii, and Project RM09-1440 at Navy installations in California. See Appendix A for a discussion of the audit scope and methodology related to the audit objective.
Descriptors:
Subject Categories:
- Administration and Management
- Economics and Cost Analysis
- Electrooptical and Optoelectronic Devices
- Military Forces and Organizations