Summary Report Ground Project Surveys for the Quarter Ended December 31, 2005

Descriptive Note:

Project assessment rept.

Corporate Author:

SPECIAL INSPECTOR GENERAL FOR IRAQ RECONSTRUCTION ARLINGTON VA

Personal Author(s):

Report Date:

2006-04-13

Pagination or Media Count:

53.0

Abstract:

We conducted 55 ground project surveys between 3 September 2005 and 5 December 2005, as part of our continuing assessments of selected sector reconstruction activities. These surveys focused on the Facilities and Transportation sectors, to include border control, education, medical and public safety facilities, as well as roads and railways. We documented site conditions using our Quality Control and Quality Assessment teams. A team comprised of an engineer and auditor reviewed and analyzed reports and photographs provided by the Quality Control and Quality Assessment teams. The review of those reports, as well as contracting documents, provides the basis for the conclusions presented in this report.

Subject Categories:

  • Administration and Management
  • Logistics, Military Facilities and Supplies

Distribution Statement:

APPROVED FOR PUBLIC RELEASE