Defense Acquisitions: Major Weapon Systems Continue to Experience Cost and Schedule Problems under DOD's Revised Policy

Descriptive Note:

Corporate Author:

GOVERNMENT ACCOUNTABILITY OFFICE WASHINGTON DC

Personal Author(s):

Report Date:

2006-04-01

Pagination or Media Count:

40.0

Abstract:

The Department of Defense DOD is planning to invest 1.3 trillion between 2005 and 2009 in researching, developing, and procuring major weapon systems. How DOD manages this investment has been a matter of congressional concern for years. Numerous programs have been marked by cost overruns, schedule delays, and reduced performance. Over the past 3 decades, DODs acquisition environment has undergone many changes aimed at curbing cost, schedule, and other problems. In order to determine if the policy DOD put in place is achieving its intended goals, we assessed the outcomes of major weapons development programs initiated under the revised policy. Additionally, we assessed whether the policys knowledge-based, evolutionary principles are being effectively implemented, and whether effective controls and specific criteria are in place and being used to make sound investment decisions.

Subject Categories:

  • Economics and Cost Analysis

Distribution Statement:

APPROVED FOR PUBLIC RELEASE