Basin F Groundwater Treatment, Interim Response Action, Phase 1, Site Investigation and Analysis, Field Investigation Work Plan.
Descriptive Note:
Corporate Author:
INTERNATIONAL TECHNOLOGY CORP ENGLEWOOD CO
Report Date:
1988-06-01
Pagination or Media Count:
32.0
Abstract:
The purpose of the Field Investigation and Analysis is to Perform a Ground Water Investigation including 1 Installation of six monitoring wells 2 Well development 3 Aquifer permeability testing 4 Ground water sampling and analysis. Sections of this plan detail information on 1 General requirements - utility clearances, site restoration, surveying 2 Drilling procedures 3 Sampling procedures 4 Well completion 6 Personnel responsibilities.
Distribution Statement:
APPROVED FOR PUBLIC RELEASE