Accession Number:

ADA273185

Title:

Final Decision Document for the Interim Response Action for the Improvement of the North Boundary System at Rocky Mountain Arsenal via Construction of Groundwater Recharge Trenches

Descriptive Note:

Corporate Author:

ROCKY MOUNTAIN ARSENAL DENVER CO

Personal Author(s):

Report Date:

1988-07-01

Pagination or Media Count:

61.0

Abstract:

The Interim Response Action IRA for the Improvement of the North Boundary System at Rocky Mountain Arsenal RMA Via Construction Of Groundwater Recharge Trenches is being conducted as part of the IRA Process for RMA in accordance with the June 5, 1987 report to the court in United States v. Shell Oil Co. and the proposed Consent Decree

Subject Categories:

  • Water Pollution and Control

Distribution Statement:

APPROVED FOR PUBLIC RELEASE