Accession Number:

ADA255234

Title:

Quality Assurance Plan for Placement of Cold-Cap Grout, Demonstration Vault, Hanford Grout Vault Program

Descriptive Note:

Final rept.

Corporate Author:

ARMY ENGINEER WATERWAYS EXPERIMENT STATION VICKSBURG MS STRUCTURES LAB

Report Date:

1992-08-01

Pagination or Media Count:

27.0

Abstract:

During FY 91, the U.S. Army Engineer Waterways Experiment Station WES developed a grout to be used as a cold cap, a nonradioactive layer, between the solidified waste and the cover blocks of a demonstration waste disposal vault at the U.S. Department of Energy Hanford Facility. This document recommends requirements for a quality assurance QA plan for field mixing and placing of the cold-cap grout during final closure of the demonstration vault. Preplacement activities emphasize selection and testing of materials that will match the performance of materials used in the WES grout. Materials sources and applicable American Society of Testing and Materials, American Concrete Institute, and American Petroleum Institute specifications and requirements are provided. Archiving of physical samples of materials is essential, in addition to careful maintenance of test reports and laboratory data. Full-scale field trial mixing and a detailed preconstruction conference are recommended. Grout, Quality assurance, Hanford.

Subject Categories:

  • Ceramics, Refractories and Glass
  • Solid Wastes and Pollution and Control

Distribution Statement:

APPROVED FOR PUBLIC RELEASE