Accession Number:
ADA204505
Title:
Compliance Testing of Eielson Air Force Base Central Heating and Power Plant, Coal Fired Boiler Number 3, Eielson Air Force Base, Alaska
Descriptive Note:
Final rept. 12-22 Jul 1988
Corporate Author:
AIR FORCE OCCUPATIONAL AND ENVIRONMENTAL HEALTH LAB BROOKS AFB TX
Personal Author(s):
Report Date:
1988-12-01
Pagination or Media Count:
143.0
Abstract:
Compliance testing for particulate and visible emissions was conducted on coal-fired boiler No. 3 in the Eielson AFB Central Heat and Power Plant on 12-22 July 88. The survey was conducted as a requirement for renewal of Alaska Department of Environmental conservation Air Quality Control permit to operate 8331-AA001. Boiler No. 3 was tested at capacities of 100,000 lbs steam hr and 90,000 lbs streamhr. Results indicate that boiler No. 3 passed the visible emissions standard, but failed the particulate emission standard. Keywords Air pollution, Emission control, Smoke stacks, Sampling.
Descriptors:
Subject Categories:
- Air Conditioning, Heating, Lighting and Ventilating