Rocky Mountain Arsenal Northwest Boundary Containment/Treatment System Construction Report. Text, Drawings, Photos

Descriptive Note:

Final rept.

Corporate Author:

ARMY ENGINEER DISTRICT OMAHA NE

Personal Author(s):

Report Date:

1986-03-01

Pagination or Media Count:

114.0

Abstract:

The Northwest Boundary Project is located along the northwest boundary of Rocky Mountain Arsenal, Commerce City, Colorado. The system was constructed to contain and treat ground water which has been polluted with organic contaminants produced at the arsenal. The system consists of 1 A Soil Bentonite cutoff barrier keyed into bedrock, 2 15 dewatering wells, 3 21 recharge wells, 4 17 piezometers, and 5 a carbon adsorption treatment plant. Foundation explorations included soil borings, bedrock sampling, ground water hydrology testing, and bedrock and soil permeability tests. Investigations during construction included visually logging well cuttings, inspection of excavated slurry trench materials, blast hole drilling, and slurry and backfill testing. Keywords Ground Water Hydrology Permeability Transmissivity Organic Contaminant Soil-Bentonite Cutoff Barrier Carbon Adsorption Dewater Wells Recharge Wells Bedrock Excavation.

Subject Categories:

  • Water Pollution and Control

Distribution Statement: