National Program for Inspection of Non-Federal Dams. Crescent Lake Dam (NH 00309), (NH No Name 107), Merrimack River Basin, Wolfeboro, New Hampshire. Phase I Inspection Report.

Descriptive Note:

Corporate Author:

CORPS OF ENGINEERS WALTHAM MA NEW ENGLAND DIV

Personal Author(s):

Report Date:

1978-10-01

Pagination or Media Count:

92.0

Abstract:

The dam is a cut stone masonry dam with a central timber section. The dam is 131 ft. long and 14.7 ft. high. The spillway of the dam is considered to be inadequate in that it can only pass 26 of the spillway test flood without overtopping the dam. There are remedial actions which should be implemented by the owner within one year of the receipts of this report.