Abstract:

The production phase of DODs weapon system acquisition process provides an area for possible cost-cutting. Within the production phase, large titanium forging lead times showed a negligible relationship to engine prices. Methods used to evaluate data were primarily descriptive statistics advanced linear regression techniques were not possible for the limited data available. Recommendations for future research efforts to clarify the research results are included.