A Product Improved Method for Developing a Program Management Office Estimated Cost at Completion.

Descriptive Note:

Research rept.,

Corporate Author:

DEFENSE SYSTEMS MANAGEMENT SCHOOL FORT BELVOIR VA

Personal Author(s):

Report Date:

1975-01-01

Pagination or Media Count:

58.0

Abstract:

This booklet describes a product improved method for developing a DOD program management office PMO estimated cost at completion EAC. The technique was developed to assist the PMO in checking the reasonableness of the EAC provided by contractors validated under the costschedule control systems criteria CSCSC. The booklet itself was designed and written to be used at the working level by PMO members of the program controlmanagement division or the businessfinance office.