Accession Number:

AD1131171

Title:

Statement of Walton H. Sheley, Deputy Director of GAO's Procurement and Systems Acquisition Division Before the Subcommittee on Military Installations and Facilities Committee on Armed Services U.S. House of Representatives

Descriptive Note:

[Technical Report, Congressional Testimony]

Corporate Author:

GENERAL ACCOUNTING OFFICE WASHINGTON DC

Personal Author(s):

Report Date:

1980-06-02

Pagination or Media Count:

13

Abstract:

We found that contract administration at the Army, Navy, and Air Force installations we visited was not adequate to prevent intentional or unintentional overcharges. Several installations paid for much more work than was done some ordered unnecessary work and accepted inferior work and lower prices were not obtained at some because requirements forecasts were unrealistic, work specifications were inappropriate or poorly written, and price proposals were not properly analyzed.

Descriptors:

Subject Categories:

  • Administration and Management
  • Logistics, Military Facilities and Supplies