Accession Number:

AD1105992

Title:

Ford-Class Carriers: Lead Ship Testing and Reliability Shortfalls Will Limit Initial Fleet Capabilities

Descriptive Note:

Technical Report

Corporate Author:

GOVERNMENT ACCOUNTABILITY OFFICE WASHINGTON DC WASHINGTON DC United States

Personal Author(s):

Report Date:

2013-09-01

Pagination or Media Count:

70.0

Abstract:

Why GAO Did This Study. The Navy plans to spend over 43 billion to produce three Ford-class aircraft carriers. The lead ship, CVN 78, is under construction, and preparation work is underway for the second, CVN 79. These ships will feature new technologies designed to increase capability and reduce crew size. GAO was asked to evaluate the progress of the Ford class. This report examines 1 technical, design, and construction challenges to delivering the lead ship within budget and schedule estimates 2 the Navys test strategy for demonstrating CVN 78s required capabilities and 3 actions the Navy is taking to improve CVN 79 cost outcomes. GAO analyzed documents related to mission requirements, acquisition plans and performance, and testing strategies, and interviewed Department of Defense DOD and contractor officials.

Subject Categories:

  • Marine Engineering
  • Economics and Cost Analysis

Distribution Statement:

APPROVED FOR PUBLIC RELEASE