Title:
Afghan Ministry of Defense Headquarters: $154.7 Million Building Appears Well Built, but Has Several Construction Issues that Should Be Assessed
Descriptive Note:
Technical Report
Corporate Author:
Special Inspector General for Afghanistan Reconstruction Arlington United States
Report Date:
2016-02-01
Pagination or Media Count:
26.0
Abstract:
WHAT SIGAR REVIEWED On April 21, 2009, the Air Force Civil Engineer Center AFCEC, previously the Air Force Center for Engineering and the Environment, awarded a 48.7 million cost-plus-fixed-fee contract to Innovative Technical Solutions, Inc. ITSI to construct a Ministry of Defense MOD headquarters in Kabul, Afghanistan. ITSI was to complete the building by October 11, 2010. After 14 modifications, the contract cost was raised to 107.3 million. By November 2013, ITSI had requested an additional 24.7 million to finish the project. However, due to a lack of available funds, construction work was halted on December 31, 2013.On July 30, 2014, AFCEC awarded Gilbane Federalthe new corporate name for ITSIa second 47.4 million firm-fixed-price contract to complete the MOD headquarters building by July 31, 2015.The five-story building included, among other things, a national command center, administration space, dining facilities, bathrooms, secure garage, a 1,000-seat auditorium, a waste water treatment plant, and a heatingcooling system.Since the building is located in an active seismic zone, a key part of its design was the separation into seven sections to avoid the transfer of forces from one section to the other. The separation joints between sections were designed to be complete breaks in the floors, walls, and ceilings that divide the building into discrete sections.The objectives of this inspection were to assess whether 1 construction was completed in accordance with contract requirements and applicable construction standards, and 2 the building was being used as intended and maintained.
Distribution Statement:
APPROVED FOR PUBLIC RELEASE