Accession Number:

AD0475641

Title:

LAND COMBAT SUPPORT SYSTEM MULTISYSTEM TEST EQUIPMENT.

Descriptive Note:

Quarterly interim technical rept. no. 4, 1 Jul-30 Sep 65.

Corporate Author:

RADIO CORP OF AMERICA BURLINGTON MA AEROSPACE SYSTEMS DIV

Personal Author(s):

Report Date:

1965-10-30

Pagination or Media Count:

131.0

Abstract:

During the third quarter of Phase II on the LCSS Program that is, April, May and June 1965, the major portion of hardware design was completed. During this, the fourth quarter of the Program, the remaining portion of hardware design was essentially completed and released to drafting. With the completion of a Definitive CPIF Phase II Contract on 13 September 1965, the hold imposed on all manufacturing activities during the third quarter was removed and the LCSS Program resumed on a full-scale basis. Author

Subject Categories:

  • Electrical and Electronic Equipment

Distribution Statement:

APPROVED FOR PUBLIC RELEASE