Title :   A Comparison of Earned Value Management and Earned Schedule as Schedule Predictors on DoD ACAT I Programs


Descriptive Note : Master's thesis


Corporate Author : AIR FORCE INST OF TECH WRIGHT-PATTERSON AFB OH SCHOOL OF ENGINEERING AND MANAGEMENT


Personal Author(s) : Crumrine, Kevin T


Full Text : https://apps.dtic.mil/dtic/tr/fulltext/u2/a582020.pdf


Report Date : Mar 2013


Pagination or Media Count : 247


Abstract : Earned Schedule, since it was introduced by Walt Lipke in 2003, has been studied extensively in a variety of different fields and on programs of all sizes. However, Earned Schedule's viability as an extension of Earned Value Management (EVM) in Major Defense Acquisition Programs (MDAP) has yet to be effectively answered. The first aspect of this research explores the breadth of Earned Schedule's adoption by the System Program Offices (SPO) of the United States Air Force. The second phase of this research explores whether Earned Schedule is a more accurate and timely schedule predictor than the EVM technique currently employed by the United States Department of Defense (DoD). A series of five descriptive statistical tests were conducted on the Earned Value data for 64 Acquisition Category (ACAT) I MDAP's. This research finds Earned Schedule to be a more timely and accurate predictor than Earned Value Management.


Descriptors :   *ACQUISITION , *COST ANALYSIS , *PROJECT MANAGEMENT , ACCURACY , AIR FORCE , COMPARISON , COSTS , DEFENSE SYSTEMS , ECONOMIC FORECASTING , MANAGEMENT , PREDICTIONS , PRODUCTION , SCHEDULING , STATISTICAL TESTS